Met The Wayne about dust and noise from the Court St paving. They're worried about lunch-service foot traffic next week. Promised a closure schedule by Friday and offered window-cling signage.
Door-to-door follow-ups on Court St — Hot & Cold and Trading Post both fine with the revised schedule. Trading Post asked again about the tree blocking their doorway.
Coordinated with the Circuit Court on sidewalk access during jury days — they need the Court St entrance clear by 8:30 AM. Logged as a recurring constraint for the contractor.
Crew briefing: water-line tie-in on the 900 block pushes one day due to a buried conduit. Will affect parking on the north curb Wed–Thu.
Walked the 'Open During Construction' window decals to Riverviews and the Academy Center. Both happy; Academy asked for two more for their box office doors.
Fielded a noise complaint from Court St Lofts about early-start equipment. Reminded crew of the 7:30 AM no-heavy-equipment rule; HOA satisfied for now.
Weekly Phase V construction coordination meeting. Reviewed the six-week look-ahead and the ribbon-cutting tentatively set for late August.
Texas Inn flagged that the temporary 'sidewalk closed' sign was steering walk-up customers away. Repositioned the sign and added a 'businesses open' A-frame.